Question: roject Management for Design and Construction Name: Project Scheduling Worksheet Date: Instructions: Months 1 2 3 4 5 6 7 8 9 When creating a
roject Management for Design and Construction Name:
Project Scheduling Worksheet Date:
Instructions: Months
When creating a "bar" to represent a Task Duration, shade the square in as follows: Task months You can fill squares with shading, or
In this simplistic schedule, we are leaving the linking arrows off. Task months X X You can fill squares with large Xs or
We will assume tasks proceed from predecessor to successor. Task months You can fill squares with scribbling.
Double check your shading of boxes to confirm no errors.
Arrange Tasks and Key Milestones in sequential order.
Place the following tasks in sequential order for a typical project. Hint: See textbook by Dykstra, Chapter for the project process and stages.
Then identify where the key Milestones are to be placed. Refer back to prior lectures on process.
TasksStages from Dykstra NOT in sequential order: Write Tasks In Sequential Order Below:
Construction
Programming & Design
Project Feasibility
PreConstruction
Closeout & Occupancy
Bidding & Negotiation
Milestone Events NOT in sequential order:
Substantial Completion
Start of Construction
The GO Decision
Final Completion
Zoning Approval
Construct a typical bar schedule for a building project.
Assumptions:
a All tasks are FinishtoStart linkages
b There is no "overlapping" tasks no fast track
c Assume one square in the grid equals one month of time
Acquisition is months
Design is months
Construction is months
Write Milestone Events Below and Draw an Arrow Pointing To Its Location
in the Left Column Between Tasks.
Example Task: Search for a site.
Example Event: Find a development site to acquire.
d Durations for various tasks are as follows: months
Construct a typical bar schedule for a building project.
Assumptions:
a All tasks are FinishtoStart linkages
b There are no "overlapping" tasks no Fast Tracking
c Assume one square in the grid equals one month of time
Acquisition is months
Schematic design is month
Zoning is months
Design Development is months
Construction Documents is months
Building Permit is months
Construction is months
Final Completion and Occupancy is month
The Owner would like to "accelerate" the project schedule from problem above and is interested in the use of the "Fast Track" method to save time.
Draw a hypothetical schedule using Fast Track to shorten the overall duration by as many months as possible, given the assumptions & restrictions below:
Assumptions:
a All tasks are FinishtoStart linkages, except "fasttracked" tasks may be overlapped not finishtostart
b Assumed restrictions to fast tracking:
The later half of Acquisition can be overlapped with the successor task.
Design Development can start when halfway into the Zoning task.
The first half of Permitting can be overlapped with Construction Documents.
The Construction task includes one month of demolition of existing structures on site, which can be overlapped with the predecessor task.
The general contractor has found a way to reduce Construction by one month to months in total.
No other tasks can be fast tracked.
c Assume one square in the grid equals one month of time
Acquisition is months
Schematic design is month
Zoning is months
Design Development is month
Construction Documents is months
Building Permit is months
Construction is months
Final Completion and Occupancy is month
f Question: By how many months can the overall schedule be shortened from the schedule in problem above
d Durations for various tasks are as follows: months
d Durations for various tasks are as follows: months
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
