Question: Rosenbrook Corporation has provided the following data from its activity-based costing system: Activity Cost Pool Total Cost Total Activity RM Assembly................................ RM710,770 37,000 machine-hours 9797.1

Rosenbrook Corporation has provided the following data from its activity-based costing system:

Activity Cost Pool

Total Cost

Total Activity RM

Assembly................................

RM710,770

37,000

machine-hours 9797.1

Processing orders..................

RM39,690

1,800

Orders 1764

Inspection...............................

RM119,116

1,940

inspection-hours 614

Activity Cost Pool

Total Cost

Total Activity RM

Assembly................................

RM710,770

37,000

machine-hours 9797.1

Processing orders..................

RM39,690

1,800

Orders 1764

Inspection...............................

RM119,116

1,940

inspection-hours 614

Data concerning one of the companys products, Product H73N, appear below:

Selling price per unit................................................

RM320.00

Direct materials cost per unit..................................

RM34.94

Direct labor cost per unit.........................................

RM49.21

Annual unit production and sales..........................

460

Annual machine-hours.............................................

510

Annual orders............................................................

80

Annual inspections...................................................

10

According to the activity-based costing system, the product contribution margin for product H73N is:

A.

RM7,275.90

B.

RM8,142.00

C.

RM108,491.00

D.

RM100,349

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!