Question: Routing File: * Aaverage efficiency is based on processing time only. A . Create a Capacity Bill ( using lot sizes ) for Z in

Routing File:
*Aaverage efficiency is based on processing time only.
A. Create a Capacity Bill (using lot sizes) for Z in the box provided. 5 pts
B. How much nominal capacity (in hours) is required of Work Center 40 to complete an order for 650
Z's.(Consider both set-up and run time)
B. The Master Production Schedule (MPS) calls for 400 units in Week 1 and 500 in Week 2 of
product Z. Fill in the Workcenter loads (minutes) for the two weeks in the table below. Can you
fulfill the MPS? Explain. 5 pts.
D. Given the current resources and inventories available, how many Z's could be produced if all
resources are utilized for their production? (5 pts.) Please fill in the tables
 Routing File: *Aaverage efficiency is based on processing time only. A.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!