Question: Routing File: * Aaverage efficiency is based on processing time only. A . Create a Capacity Bill ( using lot sizes ) for Z in
Routing File:
Aaverage efficiency is based on processing time only.
A Create a Capacity Bill using lot sizes for in the box provided. pts
B How much nominal capacity in hours is required of Work Center to complete an order for
ZsConsider both setup and run time
B The Master Production Schedule MPS calls for units in Week and in Week of
product Z Fill in the Workcenter loads minutes for the two weeks in the table below. Can you
fulfill the MPS Explain. pts
D Given the current resources and inventories available, how many Zs could be produced if all
resources are utilized for their production? pts Please fill in the tables