Question: Rowe Inc has a contract to construct a building for a price of $100. so far it has incurred $60 of costs and it estimates

Rowe Inc has a contract to construct a building for a price of $100. so far it has incurred $60 of costs and it estimates an additional $20 will be needed to finish the building. How much profit can be recognized using the percentage of completion method?