Question: S # 2 3 4 5 6 7 # Activity Design house and obtain financing NI Lay foundation Order and receive material Build house Draw
S # 2 3 4 5 6 7 # Activity Design house and obtain financing NI Lay foundation Order and receive material Build house Draw the Gant chart in the following grid. Activity W1 W2 1 Select paint Select carpet Finish work 2 Predecessor 3 1 1 2,3 2,3 5 4,6 W3 W4 W5 Time (W) 3 2 1 3 4 1 1 1 Draw the CPM and calculate the 5 parameters in each node. Calculate slack for each node. Find the critical path/s. Find the total time of the project. W6 W7 W8 W9 W10 6 7 F
Draw the Gant chart in the following grid. Draw the CPM and calculate the 5 parameters in each node. Calculate slack for each node. Find the critical path /s. Find the total time of the project