Question: s and activity times: Activity A Immediate Predecessor(s) Activity Time (weeks) 2 12 B 5 D 12 11 A B, C B D E F

s and activity times: Activity A Immediate
s and activity times: Activity A Immediate
s and activity times: Activity A Immediate
s and activity times: Activity A Immediate Predecessor(s) Activity Time (weeks) 2 12 B 5 D 12 11 A B, C B D E F G 5 I TIM G 3 7 a. Choose the correct network diagram below. OA. OB. Q S 12 D 12. 3 12 OD. S D 12 S B 12 E 11 B 12 b. Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) 2 On critical path? Slack (weeks) A B 12 5 D 12 E 11 F 5 G 3 7