Question: Sally is managing a project using earned value. She notes that her project has completed $ 3 2 , 0 0 0 worth of work,

Sally is managing a project using earned value. She notes that her project has completed $32,000 worth of work, and at this point had a planned value of $29,000. Her accounting system shows she has spent $34,000. She would report to management that the project is:
Right on Schedule
Ahead of Schedule
Behind Schedule
Overloaded Scheduled
 Sally is managing a project using earned value. She notes that