Question: SAME PROBLEM & NUMBERS AS BEFORE - USE THE SAME MRP SCHEDULE Night Shutter Inc. has to deliver an order of 250 wood shutters in

SAME PROBLEM & NUMBERS AS BEFORE - USE THE SAME MRP SCHEDULE

Night Shutter Inc. has to deliver an order of 250 wood shutters in week 6. Below is the product structure tree of the finished product. The lead times are as follows: 1 week for the shutters, 2 weeks for the frames, and 3 weeks for the wood sections. Night Shutter has 30 shutters on hand and has a scheduled receipt of 100 wood sections in week 2.

What are the gross requirements for wood sections in week 5?

880

440

250

500