Question: Same question but just couldn't get the last portion so had to do two screenshots Based on the materials requirements planning (MRP) record provided, what


Same question but just couldn't get the last portion so had to do two screenshots
Based on the materials requirements planning (MRP) record provided, what are the net requirements in Week 3? MRP RECORD Lead time = 1 week On-hand inventory = 25 Safety stock = 25 Order quantity = 100 Week 1 Week 2 Week 3 Gross requirements 5050 60 Scheduled receipts 100 Available inventory 75 25 65 Net requirements Planned order receipts 100 Planned order releases 100 40 25 0 Week 1 Week 2 Week 3 Gross requirements 50 50 60 Scheduled receipts 100 Available inventory 75 25 65 Net requirements Planned order receipts 100 Planned order releases 100 40 25 35Step by Step Solution