Question: Sample Exam Question. Try your hand on it b ) table [ [ Activity , PRECEDING ACTIVITY, table [ [ ESTIMATE IN ]

Sample Exam Question. Try your hand on it
b)
\table[[Activity,PRECEDING ACTIVITY,\table[[ESTIMATE IN],[WEEKS]]],[Start,,0],[A,Start,3],[B,A,6],[C,B,8],[F,B,4],[I,B,11],[G,F,C,3],[D,C,10],[E,D,1],[H,G,8],[J,H,E,6],[K,J,E,3],[End,K,0]]
i. Draw a precedence network diagram; determine the critical path duration and the floats on the critical path
( Marks10)
ii. Critically evaluate how getting to know the float on a schedule network diagram could be assets to the project manager. (5 Marks)
Table 4.1 Estimated durations and relationships
 Sample Exam Question. Try your hand on it b) \table[[Activity,PRECEDING ACTIVITY,\table[[ESTIMATE

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!