Question: SanaMolp management reports that its average delivery cycle time is 20.0 days; its average throughput time is 7.5 days; its manufacturing cycle efficiency is 0.32;

SanaMolp management reports that its average delivery cycle time is 20.0 days; its average throughput time is 7.5 days; its manufacturing cycle efficiency is 0.32; its average move time is 0.2 day; and its average queue time is 4.0 days: 

a. What is the wait time?

 b. What is the process time?

 c. What is the inspection time?