Question: Sasha is a project manager on a construction project, which is currently in the execution phase. One of the quality control inspectors contacts Sasha regarding

Sasha is a project manager on a construction project, which is currently in the execution phase. One of the quality control inspectors contacts Sasha regarding a concern related to the quality of concrete supplied by Lafarge, which will compromise the quality of the end product.
As first step for resolution, Sasha should _______________________.
Group of answer choices
ignore the concern as more quantity can be ordered from supplier
share the concern with all the other stakeholders to see if they agree
consult PMO for advice
communicate with the stakeholder individually to deal with the concern
send a mass email to all stakeholders to let them know the project is on time and under budget

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!