Question: Saved Help Save & Exit Subm MC Qu. 95 A job was budgeted to require 3 hours... A job was budgeted to require 3 hours

Saved Help Save & Exit Subm MC Qu. 95 A job was budgeted to require 3 hours... A job was budgeted to require 3 hours of labor per unit at $8.00 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $198,000. What is the direct labor rate variance? Multiple Choice $22,000 unfavorable $22,000 favorable $16,000 unfavorable. $16,000 favorable $6,000 unfavorable