Scenario 2 (22 points)

The contractor submitted a Request for Equitable Adjustment

(REA) in the amount of $287,500 in response to your change

order to move the Pacific Lake Dam fish counting location to Big

Falls Dam.

You received the proposal three weeks after issuing the change

order. You have determined the proposed price for the change

to be fair and reasonable based on other than certified cost or

pricing data provided by the contractor.

16. What is the supporting citation for contents of the supplemental agreement? (2 points)

a. FAR 43.204(a)

b. FAR 43.204(c)

c. FAR 43.204(c)(1)

d. FAR 43.204(c)(2)

17. Which box should be checked for Item 13 of the SF 30? (2 points)

a. Block 13A

b. Block 13B

c. Block 13C

d. Block 13D

18. What authority should be cited in Block 13 of the SF 30? (2 points)

a. FAR 43.205

b. FAR 52.243-1

c. FAR 52.243-1 Alt I

d. FAR 52.243-1, Alt II

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!