Question: Scenario 2 (22 points) The contractor submitted a Request for Equitable Adjustment (REA) in the amount of $287,500 in response to your change order to
Scenario 2 (22 points)
The contractor submitted a Request for Equitable Adjustment
(REA) in the amount of $287,500 in response to your change
order to move the Pacific Lake Dam fish counting location to Big
Falls Dam.
You received the proposal three weeks after issuing the change
order. You have determined the proposed price for the change
to be fair and reasonable based on other than certified cost or
pricing data provided by the contractor.
16. What is the supporting citation for contents of the supplemental agreement? (2 points)
a. FAR 43.204(a)
b. FAR 43.204(c)
c. FAR 43.204(c)(1)
d. FAR 43.204(c)(2)
17. Which box should be checked for Item 13 of the SF 30? (2 points)
a. Block 13A
b. Block 13B
c. Block 13C
d. Block 13D
18. What authority should be cited in Block 13 of the SF 30? (2 points)
a. FAR 43.205
b. FAR 52.243-1
c. FAR 52.243-1 Alt I
d. FAR 52.243-1, Alt II