Question: Scenario 8 . 2 - Willow A company faces the aggregate planning problem shown in the table below. Cost of regular production is $ 8

Scenario 8.2- Willow
A company faces the aggregate planning problem shown in the table below. Cost of regular production is $8 per unit, the cost of producing the same unit on overtime is $15, the cost of subcontracting is $12 per unit, and the cost of carrying a unit in inventory from one month to the next is $6.
\table[[,January,February,March,April,May],[Forecast,400,800,1200,700,300],[Beginning Inventory,100,,,,],[Regular Time,,,,,],[Overtime,,,,,],[Subcontracting,,,,,],[Ending Inventory,,,,,]]
The labor contract at the plant prohibits both overtime and subcontracting output to exceed 400 units in any five-month window. The plant capacity is 20 units per day produced using two shifts and the plant runs seven days a week. By policy, management wants to avoid stockouts.
Without actually solving the aggregate planning problem, it is safe to conclude that in the optimal solution to Scenario 8.2,
Select one:
a. the number of units made using regular time will exceed the forecast.
b. the number of units made using subcontracting will exceed the number of units made using regular time.
c. the total ending inventory will exceed the number of units made using overtime.
d. the number of units made using subcontracting will exceed the number of units made using overtime.
 Scenario 8.2- Willow A company faces the aggregate planning problem shown

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!