Question: Scenario A3: Project Status Update Context: You are the project manager for a $5 million ERP implementation at a Canadian college. The ERP implementation is
Scenario A3: Project Status Update
Context: You are the project manager for a $5 million ERP implementation at a Canadian college. The ERP implementation is positioned to replace the many disjointed, legacy systems with 8 enterprise-wide, integrated functions and finally bring the organization in the 21st century. Senior management is convinced that the success of your project could lead to long-term savings, increased efficiency, increased resilience, and security - as many of the legacy systems are no longer being supported by their vendors.You lead a core project team that includes the following people:
- ERP Integration Specialist
- Business Analyst and Scheduler
- Team Lead, Software Development (leads a sub-team of 4 resources)
- Transition Manager and Team Lead, Liaison to Operations (leads a sub-team of6 resources)
- Contract Manager to ERP vendor
Situation:
- ERP Integration Specialist:
- Is burnt out and wants a vacation, resulting in the entire project being delayed by 2 weeks. Alternatively, they will settle for temporary, specialized resource (at a total cost of $45K) being assigned to help them over the next 4 months.
- Is asking to purchase an update from the vendor (at 50K), which will address upcoming quality-related risks, as the specialist is not convinced that ERP will not seamlessly integrated with your client's backend setup.
- Business Analyst and Scheduler:
- Wants to remind you that the sponsor will cancel the project if the time delay is more than a month or if any of the 8 functionalities are lost
- Wants to remind you that your both of predecessors were exited for increasing costs over 100k
- Wants to remind you that that the PMO removed another PM for trying to skip part of the gating process
- Updates you that as of this moment the project is on-track, but is forecasting significant delays, cost overruns, or quality issues in the next cycle due to the other issues on the team
- Team lead, Software Development (leads a sub-team of 4 resources):
- Has lost one specialized resource when they took a more lucrative job with a competitor, and they are indicating that the replacement will cause a delay on the delivery of their overall component by 4-8 weeks.However, they are confident that the delay can be reduced to 2 weeks if an additional $80K is allocated to the base salary of the new hire.
- Additionally, they are requesting two (extra) junior resources ($50-60K/resource) to keep up with the original schedule as they have realized that the initial ask was too ambitious. Alternatively, if the resources cannot be hired than an additional delay of 8 weeks will need to be built-into the schedule, or 2 of the 8 ERP functions will need to be removed from the project.
- Transition Manager and Team Lead, Liaison to Operations (leads a sub-team of6 resources)
- Informs you that the VP of Finance and the Executive Director of Payroll have a rivalry that is leaking over into this project: both stakeholders want the accounting and finance management component of the ERP customized to their specific needs (which are mutually exclusive); developing customization for both would add an additional 2-6 weeks of work
- Requests to skip the beta-testing stage, in order to grant early access to end-users in the ITS department
- Informs you that the HR Department prefers its existing legacy software and would like to remove the ATS and personal management functionalities of the ERP, saving the project 8 months
- Is asking you to remove a barrier and request cooperation and systems access for Server XYZ from the PMO
- Contract Manager to ERP vendor
- Has worked well with you but has a new harassment complaint against them from a member of the procurement team; replacing the contract manager will add a time delay of 3 weeks on all contract management and vendor relations issues, and may result in the loss of vendor capabilities due to losing organizational knowledge
- Has leveraged their own relationship with the vendor for an optional promotion - where the vendor would provide their own resources to assist your team - speeding up overall implementation time by 6 weeks. (This option can only be exercised if the contract manager remains on your team.)
- Has found a loophole in the contract that could allow you to instruct the vendor to skip Quality Control process, and speed up implementation by 6 weeks.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
