Question: SCENARIO: Project CE , led by Project Manager ECE, is a complex undertaking comprising interconnected activities critical to its success. The PM oversees and coordinates

SCENARIO:
Project CE, led by Project Manager ECE, is a complex undertaking comprising interconnected activities critical to its success. The PM oversees and coordinates tasks and resources, including the development of a project schedule. In your role as the assigned engineer, you will be responsible for creating the project schedule based on the following activities:
Instruction. Based on the precedence diagram you have developed, answer the following questions:
Note:
Given that the earliest start date for all independent activities is Day 01
All answers in two(2) digit format. For instance,the answer is 2 days or Day 2- write "02"
For instances that the scenario/question is not possible, write NP
Questions:
When is the latest day Activity H can start?
When is the latest day Activity F can be finished?
When is the earliest day Activity D can start?
When is the earliest day Activity B can start?
When is the latest day Activity A can be finished?
How many day(s) is the Total Float of Activity G?
How many day(s) is the Total Float of Activity J?
How many day(s) is the Total Float of Activity D?
When is the latest day Activity U can start?
When is the earliest day Activity V can start?
When is the earliest day Activity K can start?
When is the latest day Activity Q can be finished?
When is the latest day Activity N start?
How many day(s) is the Total Float of Activity D?
How many day(s) is the Free Float of Activity Q?
Until what day can the completion of Activity D be delayed without delaying the project?
Until what day can the completion of Activity G be delayed without delaying the succeeding activity?
Until what day can the completion of Activity D be delayed without delaying the succeeding activity?
How many day(s) can Activity O be delayed without delaying the project?
How many day(s) can Activity V be delayed without delaying the succeeding activity?
What is the critical path of the project?
Determine the minimum duration (in days) of the project to be completed.
SCENARIO: Project CE , led by Project Manager

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!