Question: Scenario You are planning a very basic building project. It only includes the essential items required to build a building. Your project plan must complete

Scenario
You are planning a very basic building project. It only includes the essential items required to build a building. Your project plan must complete this building project in less than 65 days and within a budget of $100,000. This planning process will help prepare you for a much longer, more involved and realistic simulation on building a home.
Approach
There are 12 activities that need to be performed for the project to be completed. These are the rules to help you identify in which order each task needs to happen:
The Framing (B) cannot start until the Foundation (A) has been poured.
Roofing (C), Windows-Doors (D), Plumbing (E) and installation of the Electrical Wiring (F) cannot begin until the Framing (B) has been completed.
The Framing Inspection (G) cannot begin until the Roofing (C), Windows-Doors (D), Plumbing (E) and installation of the Electrical Wiring (F) has finished.
Masonry/Siding (H), Flooring (I), and Drywall (J) cannot start until the Framing Inspection (G) is finished.
Painting (K) cannot begin until Masonry/Siding (H), Flooring (I), and Drywall (J) are completed.
The Final Inspection (L) cannot begin until the Painting (K) process has been completed.
AON
Total Cost : $7,000
Project Duration: 18(Days)
A B
Project Critical Path: A, B, C, D,
E, F, G, H, I, J, K, L
Scenario You are planning a very basic building

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!