Question: Schedule delays are typically analyzed using CPM networks because A. PERT uses only 50 percent duration estimates in the schedule. B. schedules often do not
Schedule delays are typically analyzed using CPM networks because A. PERT uses only 50 percent duration estimates in the schedule. B. schedules often do not have sufficiently good resource leveling and appropriate logic constraints. C. Monte Carlo simulations are too difficult to perform once the project has started. D. while the future may be probabilistic, the past is not