Question: Schedule the following activities using CPM: ACTIVITY A B UAMU IMMEDIATE PREDECESSOR TIME (WEEKS) 2 A 3 5 B 4 C D 7 D 2

Schedule the following activities using CPM:
Schedule the following activities using CPM: ACTIVITY A B UAMU IMMEDIATE PREDECESSOR TIME (WEEKS) 2 A 3 5 B 4 C D 7 D 2 F 3 EG E F H b. What is the critical pat A-B-D-E-H O A-C-E-H O A-C-E-F-G-H O A-B-D-F-G-H c. How many weeks will it take to complete the project? Number of weeks d. Which activities have slack, and how much? OB 2 weeks :D . 1 week: E. 4 weeks. OA.4 weeks: B. 1 week :D 2 weeks. OC.2 weeks: F.2 weeks: G.2 weeks