Question: Schedule the following activities using CPM: ACTIVITY B D E F G I MUU IMMEDIATE PREDECESSOR TIME (WEEKS) 5 3 A 4 B 6 C

Schedule the following activities using CPM: ACTIVITY B D E F G I MUU IMMEDIATE PREDECESSOR TIME (WEEKS) 5 3 A 4 B 6 C D 8 D 2 F 4. EG 3 MOON OLL LL b. What is the critical path? A-B-D-F-G-H A-B-D-E-H O AC-E-F-G-H A-C-E-H c. How many weeks will it take to complete the project