Question: Schedule the following activities using CPM: ACTIVITY INMEDIATE PREDECESSOR B & P Q R S B D E 1 *&AUAH TIME (WEEKS) 1 4 3

Schedule the following activities using CPM: ACTIVITY INMEDIATE PREDECESSOR B & P Q R S B D E 1 *&AUAH TIME (WEEKS) 1 4 3 2 5 2 2 D F G WNN E, G b. What is the critical path? O, A-C-E-H O A-B-D-E-H O A-C-D-F-G b. What is the critical path? O A-C-E-H O A-B-D-E-H O A-C-D-F-G O A-B-D-F-G-H c. How many weeks will it take to complete the project? Number of weeks c. How many weeks will it take to complete the project? Number of weeks d. Which activities have slack, and how much? O C, 3 weeks; F, 1 week; and G, 1 week. 20 D, 2 weeks; G. 1 week; and H, 1 week. O'B, 3 weeks, D. 1 week; and E. 1 week. A