Schedule the project described in the following table, subject to a resource constraint of 16 men. Any
Fantastic news! We've Found the answer you've been seeking!
Question:
Task | Immediate Predecessor | Resource Requirements (man-days) | Range of Permissable Crew Sizes | |
Minimum | Maximum | |||
A | -- | 45 | 5 | 15 |
B | A | 24 | 2 | 6 |
C | A | 96 | 4 | 12 |
D | A | 50 | 2 | 10 |
E | D | 30 | 2 | 10 |
F | C | 60 | 4 | 12 |
G | C | 12 | 1 | 6 |
H | B | 35 | 5 | 7 |
I | F | 42 | 3 | 14 |
J | G, E | 24 | 3 | 8 |
K | I, J | 20 | 2 | 10 |