Question: Schedule the six jobs below on the two machines using a GANTT chart and following the scheduling rules. The start of the scheduling time is
- Schedule the six jobs below on the two machines using a GANTT chart and following the scheduling rules. The start of the scheduling time is 12:00 a.m. on 10/10/2022.
Machines
- M1
- M2
Products
- A
- B
- C
Rules
- Product A runs on M1
- Product B runs on M2
- Product C runs on M1 and M2
- Run the same color jobs back to back when possible
- For this assignment, assume 0 type change time
Jobs
- J101-A
- Product: A
- Color: Green
- Run Time: 2.0 days
- Required Completion Date: 10/16, 11:59 p.m.
- J102-C
- Product: C
- Color: Blue
- Run Time: 1.5 days
- Required Completion Date: 10/16, 11:59 p.m.
- J103-A
- Product: A
- Color: Blue
- Run Time: 3.0 days
- Required Completion Date: 10/12, 11:59 p.m.
- J104-B
- Product: B
- Color: Red
- Run Time: 2.0 days
- Required Completion Date: 10/16, 11:59 p.m.
- J105-B
- Product: B
- Color: Green
- Run Time: 2.0 days
- Required Completion Date: 10/12, 11:59 p.m.
- J106-C
- Product: C
- Color: Green
- Run Time: 2.0 days
- Required Completion Date: 10/15, 11:59 p.m.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock