Schedule Variance in dollars is the difference between what was planned to be spent ( Planned Value
Fantastic news! We've Found the answer you've been seeking!
Question:
Schedule Variance in dollars is the difference between what was planned to be spent Planned Value at a specific point in the schedule and what was actually earned Earned Value for that period.
Review Later
True
False