Question: Scheduling Q5- Job Due dates (DD) (days) Process time (PT) (days) 7 8 B 3 4 7 5 D 9 2 E 6 6 i)

Scheduling Q5- Job Due dates (DD) (days) Process
Scheduling Q5- Job Due dates (DD) (days) Process time (PT) (days) 7 8 B 3 4 7 5 D 9 2 E 6 6 i) Sequence the jobs given in the table above using the following priority rules: (a) FCFS (First Come First Served), (6) EDD (Earliest Due Date), (c) LS (Least Slack), (d) SPT (Shortest Processing Time), and (e) LPT (Longest Processing Time). ii) Compare the effectiveness of FCFS and SPT rules in terms of (a) Average completion time, (b) Average job lateness, (c) Average no. of jobs at work centers