Question: Schefter Mining operates a copper mine in Wyoming. Acquisition, exploration, and development costs totaled $9.0 million. Extraction activities began on July 1, 2016. After the
| Schefter Mining operates a copper mine in Wyoming. Acquisition, exploration, and development costs totaled $9.0 million. Extraction activities began on July 1, 2016. After the copper is extracted in approximately six years, Schefter is obligated to restore the land to its original condition, including constructing a park. The companys controller has provided the following three cash flow possibilities for the restoration costs: |
| Cash Flow | Probability | |
| 1. | $780,000 | 30% |
| 2. | 880,000 | 30% |
| 3. | 980,000 | 40% |
|
| ||
| The companys credit-adjusted, risk-free rate of interest is 4%, and its fiscal year ends on December 31. (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided. Round other intermediate calculations to the nearest whole dollar. Enter your answer in whole dollars.) |
| Required: | |
| 1. | What is the initial cost of the copper mine? |
| 2. | How much accretion expense will Schefter report in its 2016 income statement? |
| 3. | What is the book value of the asset retirement obligation that Schefter will report in its 2016 balance sheet? |
| 4. | Assume that actual restoration costs incurred in 2022 totaled $943,000. What amount of gain or loss will Schefter recognize on retirement of the liability? (Loss amount should be indicated by a minus sign.) |