Question: Schurz Corporation's management reports that its average delivery cycle time is24 days, its average throughput time is14.0 days, its manufacturing cycle efficiency (MCE) is0.20, its
Schurz Corporation's management reports that its average delivery cycle time is24 days, its average throughput time is14.0 days, its manufacturing cycle efficiency (MCE) is0.20, its average move time is0.5 day, and its average queue time is3.0 days.
Required:
Round your answer to 1 decimal place.
What is the Wait Time?
days
Process Time?
days
Inspection Time?
days
3 points
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock