Question: Schurz Corporation's management reports that its average delivery cycle time is24 days, its average throughput time is14.0 days, its manufacturing cycle efficiency (MCE) is0.20, its

Schurz Corporation's management reports that its average delivery cycle time is24 days, its average throughput time is14.0 days, its manufacturing cycle efficiency (MCE) is0.20, its average move time is0.5 day, and its average queue time is3.0 days.

Required:

Round your answer to 1 decimal place.

What is the Wait Time?

days

Process Time?

days

Inspection Time?

days