Question: Schurz Corporation's management reports that its average delivery cycle time is 22 days, its average throughput time is 11.0 days, its manufacturing cycle efficiency (MCE)

Schurz Corporation's management reports that its average delivery cycle time is 22 days, its average throughput time is 11.0 days, its manufacturing cycle efficiency (MCE) is 0.20 , its average move time is 0.4 day, and its average queue time is 4.0 days. Required: a. What is the walt time? (Round your answer to 1 decimal place.) b. What is the process time? (Round your answer to 1 decimal place.) c. What is the inspection time? (Round your Intermedlate calculations and final answer to 1 decimal place.)