Question: SCM 3 0 0 - ONLINE LAB EXERCISE # 2 LINE BALANCING Module 3 Line Balancing Exercise SCM 3 0 0 AZ Devices manufactures a

SCM 300- ONLINE LAB EXERCISE #2 LINE BALANCING
Module 3
Line Balancing Exercise
SCM 300
AZ Devices manufactures a number of different electronic devices. One of their products is AZ-750 calculator. Calculators are sold every day of the month, but are only produced at the factory 5 days per week, Monday through Friday.
Their monthly demand for these calculators is 8140. The factory is open 8 hours per day. Assume an average of 22 working days per month in the factory. You will be using daily demand, so use this information to calculate the daily demand.
LINE BALANCING - PRECEDENCE DIAGRAM
Remember, the factory is open 22 days per month. The assembly line runs 8 hours per day. The following precedence diagram gives the necessary data to answer the line balancing related questions that follow.
17
A
obrace()61
71
LINE BALANCING - PROBLEMS
Question #1-Make sure this answer is correct before moving on.
What is the CYCLE TIME that ensures the desired output rate?
(NOTE: NEVER ROUND-UP YOUR CYCLE TIME!!! You should be able to figure out why this should never be done. Think about it.)
Question #2
What is the theoretical minimum number of workstations?
(ALWAYS ROUND UP workstations. Again, you should know why,)
As you know, you should always round up your theoretical minimum number of workstations. Nonetheless, be aware that the calculated theoretical minimum number of workstations is not always attainable.
S
CM 300
-
ONLINE
LAB
EXERCISE #2
LINE
BALANCING
Question #3
If someone were to create an assembly line that had
the theoretical number of
workstations
, what would the efficiency of that assembly line be?
Question #4
If someone were to create an assembly line that had the theoretical number of
workstations, what wo
uld the total amount of idle in that assembly line?
Question #5
If someone were to create an assembly line that had 10 workstations, what would the
efficiency of that assembly line be?
Question #6
If someone were to create an assembly line that had 10 wo
rkstations, what would the
total amount of idle in that assembly line?
 SCM 300- ONLINE LAB EXERCISE #2 LINE BALANCING Module 3 Line

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!