Question: Scope Statement: Project Title: Dai-Ichi Corporation Australia (DCA) SAP Project Phase 1 Date: Prepared by: Project Background: The Dai-Ichi Corporation is a major international player

Scope Statement:

Project Title: Dai-Ichi Corporation Australia (DCA) SAP Project Phase 1

Date:

Prepared by:

Project Background:

The Dai-Ichi Corporation is a major international player in the mining industry. The head office in Italy has recently completed the rollout of SAP for its European headquarters. The decision has been made to deploy the same platform into the Oceania operations commencing with Australia. Given the distance and time zone difference, a decision was also made to deploy the SAP instance on the cloud. This will facilitate the SAP instance to be managed out of Europe.

Final negotiations for cloud resources has been completed between Amazon and Dai-Ichi Europe. The Australian team will be the first Cloud SAP instance for the Dai-Ichi group. As such it was decided to break the project down into different phases. You have been appointed as the project manager of the pilot phase and you have been given the following resources.

You team comprises the following:

1) PauloMossimo-SAPExpertfromItalyfamiliarwithdeployingSAPinhouse

2) SanjaySrivastava-CloudArchitectrecentlyhiredfromHPwithexperience

deploying Amazon Web Services

3) JuneSmith-SAPExpertrecentlyhiredfromFujitsu.

4) LarryJones-LinuxApache,MySQL,Cprogrammer.LAMPSpecialist.

5) JennyHarvey-LinuxAdminandLAMPSpecialist.

Your brief is to set up a test instance of SAP on the AWS cloud infrastructure. You have 12 weeks to get the first instance of the SAP up and running. Since Cloud resources are instant on resources, it is assumed that you can start immediately.

A total of 20 Cloud servers are available for you to create the SAP instance. You dont need to use all of them as they cost $2750.00 per month per instance.

The configuration of the Test Instance is as follows:

2 x Database Servers 2 x Application Servers 3 x Web Services Layer Servers

ISYS302 Assignment One Page 3 Semester 1, 2015

Project Resource List

Staff

No

Price

Project Manager yourself

1

$2000 per day

Paulo SAP Expert assume Paulo is available from day 1

1

$2000 per day

Sanjay Cloud Architect

1

$7,500 / Month

June SAP Expert

1

$7,500 / Month

Larry Jones LAMP Stack Specialist

1

$3,500 / Month

Jenny Harvey Linux Administrator + LAMP

1

$3250 / Month

Amazon Cloud Infrastructure

Instance

Price

X 86 image per instance

$2,750 per month

Software

SAP Cloud Instance Site License for Australia

1

$200,000

JIRA

10

$50 per seat

Miscellaneous Costs

Qty

Price

Travel & Accommodation Expenses for Paolo

1

$10,000 per month

The management team is very keen on getting this phase completed within the budgeted 12 weeks. You would like to be on time and impress the management team so that you can considered for the next phase of the project. You have decided to adopt JIRA as the issue tracking and project management tool. You used it in your last job/project and feel that it can help you succeed with this large project.

Planning ISYS302 Assignment Two Page 4 Semester 1, 2018

Deliverables of Part 1 MS Project File (100 Marks)

This component requires some preparation and then data entry into the MS Project file as follows:

1.1 Create a WBS (Work Breakdown Structure for the Dai-Ichi SAP Cloud Pilot. see Schwalbe pg. 198-208) for the above scope of work and translate this into a task list in MS Project 2013. Add dependencies and durations to create a Gantt chart (See Appendix A Schwalbe for detailed instructions on how to use MS Project to create a Gantt Chart). You might want to consider adding regular Steering Committee meetings and communications to specific stakeholders on the progress of the project.

SYS302 Assignment Two Page 4 Semester 1, 2018

Deliverables of Part 1 MS Project File (100 Marks)

This component requires some preparation and then data entry into the MS Project file as follows:

1.1 Create a WBS (Work Breakdown Structure for the Dai-Ichi SAP Cloud Pilot. see Schwalbe pg. 198-208) for the above scope of work and translate this into a task list in MS Project 2013. Add dependencies and durations to create a Gantt chart (See Appendix A Schwalbe for detailed instructions on how to use MS Project to create a Gantt Chart). You might want to consider adding regular Steering Committee meetings and communications to specific stakeholders on the progress of the project.

Example Tasks to consider (this is not an exhaustive list!)

Initiating Define Project Scope, time and costs constraints and high-level requirements (done) Form project team (done)

Develop Project Plan, Schedule and Detailed Budget (what you are doing in this assignment) Obtain sign off on plan (signals approval by steering committee to start implementation)

Design/Build/Test Detailed requirements gathering

Go Live Close out project

1.2 Provide the critical path for your implementation. Illustrate your critical path using a sequence of nodes and edges along the following lines.

1.3 Add resources to your Gantt Chart and print a resource based task list (who does what when, view of the project) for your own reference.

1.4 Finalise your pricing and technical specs and calculate your budget. 1.5 Microsoft Project File.

1.5.1. Implement the project scope into MS Project 2013 (or 2010), showing costing and indenting subtasks appropriately.

a. Usetheoutlinenumberingfeaturetodisplaytheoutlinenumbers.For example your WBS should start with

i. 1.0 Initiating... b. Enter any duration or dependencies c. Allocate resources d. Show costing for your staff members e. Document WBS and insert into MS Project.

f. Cut and paste into Project Report: i. Gantt Chart ii. Network Diagram showing critical path iii. Resource Schedules

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!