Question: SCOPE You work for Rocket City Consulting LLC . You are the project manager for automating the painting of rocket bodies. The rocket designers have

SCOPE
You work for Rocket City Consulting LLC. You are the project manager for automating the painting of rocket bodies. The rocket designers have specified a tight tolerance on the thickness and even distribution of paint on the exterior of the rocket. Your job is to construct the automated painting facility. The overall cost of the project has been estimated to be $2,000,000 and is scheduled to begin on 5 Feb 2024. The customer requires the system to be ready for the first rocket body by Labor Day.
The construction of the building is subcontracted by your company to Athens Construction. The robot assembly, installation, and certification are subcontracted to Swissbots from Geneva, Switzerland.
Table 1. Project PaintBot Scope
SCOPE BUDGET CONTRACTOR
Building $1,310,000 Athens Construction
Install Robot $310,000 Athens Construction
Swissbots
Program and Certify $380,000 Swissbots
Total $2,000,000
SCHEDULE
Based on the scope, you have broken the project into three (3) milestones.
Building
The building begins with excavating the land and pouring the foundation. The next task is to assemble metal structure of the building. Inside of the structure, a paint booth with required lighting and ventilation is assembled. Finally, a concrete stand is framed and poured to hold the traversing rail system.
Table 2. Building Estimate
Foundation 15 days $160,000
Structure 60 days $600,000
Paint Booth 12 days $350,000
Robot Stand 10 days $200,000
Total 97 days $1,310,000
Installation
With the building complete, the robot installation begins. The traversing rails are installed on top of the stand to allow the robot to move back and forth along the length of the rocket body. The robotic arm and sprayer is installed on top of the traversing rails.
Table 3. Installation Estimate
Install Traversing Rails 14 days $260,000
Assemble Robot 14 days $50,000
Total 28 days $310,000
Program and Certify
The final milestone is to program and certify the machine for use by the customer. This involves programming the robot to operate in the new facility and train the robot to navigate around the rocket structure. Next, the machine will be put through a series of tests to verify the performance culminating in a certification. Finally, the customer is trained on the operation and maintenance of the robot and the facilities.
Table 4. Program and Certification Estimate
Program and Train Robot 7 days $100,000
Testing and Certification 13 days $240,000
Train Customer 5 days $40,000
Total 25 days $380,000
STATUS
Tuesday, June 18,2024, you are completing your update to the project status to account for issues that have occurred.
The first issue occurred with a cost of over $200,000 in the construction of the structure. The initial design did not account for a change in municipal building code requiring an advanced fire detection and suppression system.
The second issue occurred with the construction of the robot stand. A major ice storm has hit the area causing the city to shut-down. After the ice thawed, the concrete supplier had delays on the manufacturing capability operational. The current state of the stand build is 70% complete.
Table 5. Project Status as of June 18,2024
WBS Task Duration Baseline Cost % Actual Complete
1 Project PaintBot
1.1 Building
1.1.1 Foundation 15 days $160,000100%
1.1.2 Structure 60 days $600,000100%
1.1.3 Paint Booth 12 days $350,000100%
1.1.4 Robot Stand 10 days $200,00070%
1.2 Install Robot
1.2.1 Install Traversing Rails 14 days $260,000
1.2.2 Assemble Robot 14 days $50,000
1.3 Program and Certify
1.3.1 Program and Train Robot 7 days $100,000
1.3.2 Testing and Certification 13 days $240,000
1.3.3 Train Customer 5 days $40,000
CUSTOMER UPDATE
Fancy Rockets is not happy with the project progress. The project has not cleared the first milestone and there is a cost overrun and a delay in schedule. Fancy Rockets has called a meeting for today (Tuesday, June 18,2024) to understand the situation.
1. What did you plan to spend constructing the building for the robot?
2. What has actually been spent to date?
3. How work completed till now?
4. What was the total project supposed to cost?
5. What cost inefficiency is the project experiencing?
6. What schedule inefficiency is the project experiencing?
7. How much is the project overspending?
8. What is the cost required to complete the project?
9. What is the final cost if the future expenditures occur at the original forecasted amount?
10. What is the estimate assuming that the project continues to spend at the same rate?
11. What is the required future work performance to complete the project by Labor Day?
12. What is the required future cost performance to complete the project at the original budget?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!