Question: Scotsburn Dairy: The MPS Problem The master scheduling problem at Scotsburn is to determine the production quantity for the products during each week for the
Scotsburn Dairy: The MPS Problem
The master scheduling problem at Scotsburn is to determine the production quantity for
the products during each week for the next weeks subject to the limitation of
production hours imposed by the aggregate production plan. Because some products
have "joint" setup, it is more efficient to group them as a family if possible. For example,
some products are made from the same base mix eg no sugar and some use the
same tub size eg two litres Changing base mix on a line requires washing all the
equipment, and changing the tub size requires physical adjustment to the filling and
packaging equipment. Either action requires approximately a halfhour, and changing
base mix also results in approximately $ of wasted mix. Exceptions include
multiflavour products eg Neapolitan ice cream which require tight coordination of
flavours, and products containing a particular allergen eg peanuts In these cases,
all sizes of these products should be included in their own family. Within a family, a
flavour or fruit change requires approximately five minutes.
Sccotsburn produces tens of families of ice cream and frozen yogurt on three lines. For
simplicity, we assume two families, one line, and only three weeks. Suppose that the
setup time for each family is one hour, cost of labour involved in changeover is $ per
hour, and cost of mix loss is $ Holding cost rate is percent per year, cost of one
litre of ice cream is $ and there are workweeks per year.
The demand in production hours for each family per week after adjusting for initial
inventories and safety stocks during the next three weeks are as follows:
The aggregate production plan has specified hour weeks four days of hours
each during these three weeks.
Question
What feasible set of lot sizes for each family in each week will minimize total setup and
holding cost? A feasible set of lot sizes will meet the demand during the next three
weeks within hour weeks. Assume that a week's demand for a family cannot be split
between two weeks.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
