4.(Slack time) In the following project, what are the earliest start, latest start, and slack time for each task?
IP: Immediate Predecessors
ET: Estimated Time
ES: Earliest Start
LS: Latest Start
ST: Slack Time
IP
ET
ES
LS
12
A
B
A
10
C
B
B
A
C
D
A
15
J
E, G, H
F, I, J
6
ST
9
10
24
10
35
40
4
K
D
E
F
G
H
I
A
D
15
E, G, H 4
\table[[,IP,ET,ES],[A,-,12,0],[B,-,9,0],[C,A,10,12],[D,B,10,9],[E,B,24,?
 Screenshot 2024-03-22 at... (i) (4) 4.(Slack time) In the following project,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!