Question: SCS Co. uses activity-based costing in their manufacturing process. The company produces two products, ABC and XYZ. SCS has provided their costing department the following

SCS Co. uses activity-based costing in their manufacturing process. The company produces two products, ABC and XYZ. SCS has provided their costing department the following information from this years budget relating to the production of these two products:

ABC XYZ
Units to be produced 4,000 6,000
Machine-hours expected 100 200
Direct labor-hours expected 200 300
Materials handling (number of moves) 60 70
Machine setups (number of setups) 20 15

The following costs are expected to be incurred throughout the year, and are related to the cost drivers being measured:

Direct Labor Wages $50,000
Materials handling 4,000
Labor-related overhead 42,000
Machine setups 7,000

What is the expected overhead allocated per unit of product ABC? NOTE: Round all per-unit costs to nearest cent.

a. $10.30

b. $30.77

c. $84.00

d. $200.00

e. None of the above

What is the total expected overhead allocated to product XYZ? NOTE: Round all per-unit costs to nearest cent.

a. $22,646.20

b. $27,353.90

c. $28,200.00

d. $30,353.90

e. None of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!