Question: Second consulting is considering undertaking several proposed projects for the next fiscal year. The projects, the number of engineers and support personnel required for each
Second consulting is considering undertaking several proposed projects for the next fiscal year. The projects, the number of engineers and support personnel required for each project, and the expected profits for each project are summarized in the following table:
| Project | ||||||
| 1 | 2 | 3 | 4 | 5 | 6 | |
| Engineers required | 20 | 55 | 47 | 38 | 90 | 63 |
| Support personnel required | 15 | 45 | 50 | 40 | 70 | 70 |
| Profit ($1,000,000s) | 1.0 | 1.8 | 2.0 | 1.5 | 3.6 | 2.2 |
There are 175 engineers available and 150 support personnel available for these projects. Further, no more than 3 projects can be done. Formulate an integer program to solve this problem.
- Define the decision variables needed to model this problem.
- The objective is to maximize profit. Give the objection function.
- Write the constraints.
- What is the final answer? Explain in detail.
Use Excel Solver
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts