Question: Second consulting is considering undertaking several proposed projects for the next fiscal year. The projects, the number of engineers and support personnel required for each

Second consulting is considering undertaking several proposed projects for the next fiscal year. The projects, the number of engineers and support personnel required for each project, and the expected profits for each project are summarized in the following table:

Project

1

2

3

4

5

6

Engineers required

20

55

47

38

90

63

Support personnel required

15

45

50

40

70

70

Profit ($1,000,000s)

1.0

1.8

2.0

1.5

3.6

2.2

There are 175 engineers available and 150 support personnel available for these projects. Further, no more than 3 projects can be done. Formulate an integer program to solve this problem.

  1. Define the decision variables needed to model this problem.
  2. The objective is to maximize profit. Give the objection function.
  3. Write the constraints.
  4. What is the final answer? Explain in detail.

Use Excel Solver

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!