Question: Secondary risks are most likely to be identified? A. Just after the Implement Risk Responses process B. During the Perform Quantitative Risk Analysis process C.
Secondary risks are most likely to be identified? A. Just after the Implement Risk Responses process B. During the Perform Quantitative Risk Analysis process C. Just before the Plan Risk Responses process D. During the Plan Risk Responses processIn order to mitigate the risk of having less than adequate team members on a project, the project manager hires more team members, creating the risk of having inadequately trained team members. This latter risk is an example of a A. Subtending risk B. Secondary risk C. Residual risk D. Derivative risk
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
