Question: Section 1 Unit 5 Homework Q 3 Question 3 Using the table below, which WBS element is over budget and behind schedule? Select one: a.

Section 1 Unit 5 Homework Q 3 Question 3 UsingSection 1 Unit 5 Homework Q 3 Question 3 Using the table below, which WBS element is over budget and behind schedule? Select one: a. Element A b. Element D c. Element C d. Element

WBS Element B PV EV AC $1,000 $1,100 $1,150 $2,000 $1,800 $2,100 $1,000 $1,200 $1,050 $2,000 $1,900 $1,800 D