Question: . Section 4 : Calculations ( 6 marks ) i . Write your answer in the booklet provided ii . Each question carries 3 marks

.
Section 4: Calculations (6 marks)
i. Write your answer in the booklet provided
ii. Each question carries 3 marks
iii. Answer any two (2) questions
Q1. You are running a project in one of your company's manufacturing plant. After 25 weeks of the project, your earned value dataset is shown below. Use the information provided to answer the questions below. The project is planned to end in week 30, with planned budget of \(\$ 135000\). You are currently at the end of week 25. Describe what the results of each calculation mean to you as a project manager. The values are in dollars.
i. What is the estimated Schedule Variance (SV) and its interpretation?
ii. What is the estimated Cost Variance (CV) and its interpretation?
iii. What is the estimated SPI and its interpretation?
iv. What is the estimated CPI and its interpretation?
v. Based on current performance, what is cost 'Estimate at Completion' (EAC)?
4
 . Section 4: Calculations (6 marks) i. Write your answer in

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!