Question: SECTION A - MULTIPLE CHOICE ( 2 5 Questions - 5 0 Points ) Please circle the correct answer ( only choose one ) for

SECTION A - MULTIPLE CHOICE (25 Questions -50 Points)
Please circle the correct answer (only choose one) for the following 25 questions.
Which party is mainly responsible for mobilization?
A. Owner
B. Construction manager
C. Architect engineer
D. General Contractor
The three main activities during project close out are:
A. Project completion close out, Construction close out, Owner close out
B. Construction close out, Contract close out, Contractor close out
C. Contractor closes out, Owner closes out, Sub contractor closes out
D. Contract close out, Budget close out, Schedule close out
WBS stands for:
A. Work breakdown structure
B. Work below schedule
C. Work before sunrise
D. Work by schedule
In determining the logical relationships between construction activities, the three main types of Imposed Precedence are:
A. Procedural, Technical, State
B. State, Environmental, Resource
C. Technical, Environmental, State
D. Resource, State, Environment
E. None of the above
In the Linear Scheduling Method (LSM), if the rate of progress of the successor activity is slower than the rate of progress of the predecessor activity, then it is up to the contractor to decide whether to maintain the minimum buffer (e.g., a buffer of at least 100 yards) between the starting times of the two activities to prevent interference.
A. True
B. False
Activities that are not on the critical path always have FF that is greater than zero:
A. True
B. False
A project with a Cost Performance Index (CPI)1 is a project that is:
A. Over budget
B. Ahead of Schedule
C. Under budget
D. Behind Schedule
SECTION A - MULTIPLE CHOICE ( 2 5 Questions - 5 0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!