Determine the critical path for the following project using slack. You are required to first develop an AON network diagram for the project.
\table[[Activity,Immediate Predecessor,Duration (Days)],[A,------,4],[B,------,6],[C,------,6],[D,A,4],[E,B, C,4],[F,C,9],[G,D, E,5],[H,F,3],[I,H,12],[J,G,8],[K,I. J,6]]