Determine the critical path for the following project using slack. You are required to first develop an AON network diagram for the project.
\table[[Activity,Immediate Predecessor,Duration (Days)],[A,dots---,4],[B,dots----,6],[C,A,6],[D,B, C,4],[E,C,4],[F,D, E,9],[G,F,5],[H,H,3],[I,G,12],[J,I. J,8],[K,,6]]