Question: SECTION B MANAGEMENT ACCOUNTING [ 5 0 MARKS ] QUESTION 1 ( 2 5 Marks ) Jurupa Ltd , a construction company based in Kondinin,

SECTION B MANAGEMENT ACCOUNTING [50 MARKS]
QUESTION 1(25 Marks)
Jurupa Ltd, a construction company based in Kondinin, Madron has been awarded a contract
by the Cricket World Cup Federation Committee to build the concrete stadium seats for the new
stadium located in Fred Point, Durban. The company director, Bruce Gianni, has appointed
Sujik Bratiko as the production manager with a salary of R100000 per month.
MBA4807
OCT/NOV 2023 SUPPLEMENTARY EXAMINATION
6
The concrete to manufacture each seat cost R55.00 per seat. Sujik has estimated that it would
take 12 hours to make one seat in the production process at a wage rate of R296.00 per hour
worked with a workforce of one hundred workers in the process. With all the labour hours being
worked, the concrete mixers are estimated to lose R63525 in value every year.
The company had to spend an additional R362565 for costs incurred to put sign boards at the
different corners of the stadium informing the public that the company is manufacturing the
seats for the new stadium, this is an excellent marketing tool for the company. The construction
site requires a site office to be set up. ManStrong Container Rentals agreed to set up a container
for the company in order to operate the office at a rate of R36000 per month. The site will also
employ, Thanda McNeil to do the administration work for the site office at a salary of R29500
per month.
As a result of expensive materials and equipment being kept at the site, the managers agreed
that a security company must be contracted to guard all materials and equipment used in
production. After a tender process, Shape Security had been awarded the contract which stated
they would provide 2\times 24-hour armed guards per shift for a rate of R65963 per month.
Required:
Identify all the costs involved from the information provided above, then classify the cost
you have selected in terms of Cost Behaviour (Variable, Fixed or Mixed Cost) and then
further classify the cost as either Product Cost (Manufacturing Cost) or Period Cost
(Non-Manufacturing Cost).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!