Question: Section C: Case-based Project Management practice ( 4 0 marks) Section C consists of Project Management exercises and may require you to produce appropriate charts,
Section C: Case-based Project Management practice (40 marks)
Section C consists of Project Management exercises and may require you to produce appropriate charts, figures, and Project management software output. Each question has detailed instructions for you and you must answer all questions.
Case: D company is developing a new massive storage device project. The activities below are identified and you are assigned as the project manager. The project start date is June 1st, 2020. Please answer the following 3 questions.
Activities related to the project along with duration and interdependency are defined below.
| Massive storage device project | |||
| Activity ID | Description | Predecessor | Duration (workdays) |
| 1 | Define scope | None | 6 |
| 2 | Define customer problems | 1 | 3 |
| 3 | Define data records and relationship | 1 | 5 |
| 4 | Massive storage requirements | 2,3 | 5 |
| 5 | Consultant needs analysis | 2,3 | 10 |
| 6 | Prepare installation network | 4,5 | 3 |
| 7 | Estimate costs and budget | 4,5 | 2 |
| 8 | Design section pint system | 4,5 | 1 |
| 9 | Write request proposal | 4,5 | 5 |
| 10 | Compile vendor list | 4,5 | 3 |
| 11 | Prepare management control system | 6,7 | 5 |
| 12 | Prepare comparison report | 9,10 | 5 |
| 13 | Compare system philosophies | 8,12 | 3 |
| 14 | Compare total installation | 8,12 | 2 |
| 15 | Compare the cost of support | 8,12 | 3 |
| 16 | Compare the customer satisfaction level | 8,12 | 10 |
| 17 | Assign philosophies points | 13 | 1 |
| 18 | Assign installation cost | 14 | 1 |
| 19 | Assign support cost | 15 | 1 |
| 20 | Assign customer satisfaction points | 16 | 1 |
| 21 | Select the best system | 11,17,18,19,20 | 1 |
| 22 | Order system | 21 | 1 |
Note:1. The weekend is not calculated as a workday, please ignore holidays.
2. Assume Earliest finish date = Latest finish date.
3. Use the legend below for the project network chart.
4. Project network chart and Gantt chart-please insert the two charts directly in your word file when submitting or as attached files. Make sure all the dates and numbers are clear when inserting.
| Legend | ||
| ES | Activity ID | EF |
| SL | Description | |
| LS | Duration | LF |
Questions:
- Please use the legend above to draw a project network chart(8), indicating ES, EF, LS, LF, and SL in each of the activities of the node.8