The project is an extension to an existing university building providing more lecture space. The work has been procured using the NifCA Engineering and Construction Contract main Option A and secondery Options and The aueument inferval is a calendar month.
GO TO NEXT UNANSWERED OUESTIOW
QUESTION
Which of the following statements best describes the purpote of the Activity Schedule in the contract described in this question?
Select ONE option.
The Activity Schedule is used to assess compensation events.
The Activity Schedule is used to assess the amount due and is not Scope or Site information.
The Activity Schedule is used to assess the changes to the total of the Prices and is not Scope or Site Information.
The Activity Schedule is used to assess the Price for Work Done to Date and is not Scope or Site Information.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock