Question: see below activity duration , predecessor table . determine the total project completion time in terms of integers See below activity duration, predecessor table. Determine

see below activity duration , predecessor table . determine the total project completion time in terms of integers
see below activity duration , predecessor table .
See below activity duration, predecessor table. Determine the total project completion time, in terms of integers. Activity Time (days) Immediate Predecessor(s) A 3 2. B 1 loo 6 E 2 BD F 6 A, E G 1 A, E I 3 F 10 G J 14 K 2 HI