Question: See the resources needed for each activity and the corresponding calendar. Add the resources to your calendar (below). For any given day an activity takes

See the resources needed for each activity and the corresponding calendar. Add the resources to your calendar (below). For any given day an activity takes place, the workers per day are the required number of workers to complete the activity for that given dayno splitting workers.

Hint: IN represents interfering float. F represents free float. The schedule has already been placed into a calendar with additional holidays. Do not schedule workers over the weekend or during the holidays!

  1. Determine what the required resources are in workers per day.
  2. You have a maximum ability to hire 6 workers per day. Can you level the schedule to complete your job on time? If so, what would the leveled schedule look like? If not, explain why not and level the schedule to show the new project schedule and duration that accommodates the resource constraints.

See the resources needed for each activity and

Activity Duration PIB workers per day 5 2 None 1 10 3 3 None 1 15 3 5 2 20 4 5 5 2 25 1 10 1 30 N 15 2 2. 35 2 25 3 40 5 20, 30, 35 1 MTW Th F Sa Su MT W Th F TW Sa Su MT w Th Activity 1 2 3 4 5 6 7 00 9 10 11 12 13 14 15 16 17 18 5 10 IN 15 20 F 25 IN 30 35 F 40

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!