Question: Select a statement that best describes the following PMBOK process activity: Develop Team Question 14 Select one: a. Defining how to estimate, acquire, manage and

Select a statement that best describes the following PMBOK process activity:

Develop Team

Question 14 Select one:

a.

Defining how to estimate, acquire, manage and utilize physical and team resources

b.

Tracking team member performance, providing feedback, resolving issues and managing team changes to optimizes project performance.

c.

Ensuring physical resources assigned and allocated to the project are available as planned as well as monitoring the planned versus the actual use of resources and performing corrective action as necessary.

Ensuring physical resources assigned and allocated to the project are available as planned as well as monitoring the planned versus the actual use of resources and performing corrective action as necessary.

Ensuring physical resources assigned and allocated to the project are available as planned as well as monitoring the planned versus the actual use of resources and performing corrective action as necessary.

d.

Improving competencies, team member interactions and the overall environment to enhance project performance

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!