Question: Select all that were the source for the Direct Labor favorable effeciency variance. a . Actual number of jobs completed was greater than budgeted number

Select all that were the source for the Direct Labor favorable effeciency variance.
a. Actual number of jobs completed was greater than budgeted number of jobs.
b. Actual direct labor hours per job were greater than budgeted direct labor hours per job.
c. Actual direct labor hours per job were less than budgeted direct labor hours per job.
d. Actual number of jobs completed was less than budgeted number of jobs.
e. Actual direct labor cost per hour was greater than budgeted direct labor cost per hour.
f. Actual direct labor cost per hour was less than budgeted direct labor cost per hour.
QUESTION 3
Select all that were the source for the Indirect Costs unfavorable rate variance.
a. Actual number of direct labor hours per job was less than budgeted direct labor hours per job.
b. Actual number of jobs completed was less than budgeted number of jobs.
c. Actual number of jobs completed was greater than budgeted number of jobs.
d. Actual number of direct labor hours per job was greater than budgeted direct labor hours per job.
e. Actual indirect costs per direct labor hour was greater than budgeted indirect cost per direct labor hour.
 Select all that were the source for the Direct Labor favorable

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!