Question: Select the best statement which describes the dynamics present in this project, given the results shown in the tables? A. With normal times, this project
Select the best statement which describes the dynamics present in this project, given the results shown in the tables?
A. With normal times, this project can be done in 100 days at a cost of 185,000.
B. With normal times, this project can be completed in 59 days at a cost of $185,000.
C. This project can be done in as low as 46 days if we invest an additional 31,000 in it.
D. Both B and C are correct
E. Both A and C are correct